Understructure and Corridor of Wagon Tippler Shed of Huanghua Port Phase I Project
时间:2018-11-15 source:本站


Commencement time:1999-3-1

Completion time:2001-9-28

ntroduction:The envelope structure for earth excavation of the wagon tippler shed adopts the structure form of diaphragm wall, ring beam and longitudinal rib, and the excavation depth of the main body is 18.3m. The understructure of the wagon tippler shed consists of the floor, perimeter wall (with buttress), funnel girder, middle partition wall, equipment foundation and other main structures; the corridor includes a single-hole corridor and a double-hole corridor.