Mauritania Bumu - Saineibabi Lot 3 Highway Project
时间:2018-11-15 source:本站
Commencement time:2009-1-1
Completion time:2011-7-21
Introduction:the project is located in the
Mauritania Mubu - Saineibabi region, and is the third lot of Kaidi - Mubu -
Saineibabi highway engineering, which connects 2 important cities of Mubu and
Saineibabi. Mubu-Saineibabi section is invested by Mauritania government. The lot
is from Mubu to Saineibabi, and the total length is 117km. Mauritania AGRINEQ
Company jointly win the bid the implement the project. There are many river
valleys along the line in the project, changes in water level are large, and
there are many bridge and culvert structures, and 102 box culverts. A 36.6m
bridge is constructed in Saineibabi, which is the first bridge designed and
constructed by our company in Mauritania.