Beijing-Shanghai Expressway Phase I Project Lot 3
时间:2018-11-14 source:本站
Commencement time:2004-3-15
Completion time:2005-9-30
Introduction:The total length of embankment grand bridge of the project is
2266m, the lower structure form of the bridge is: Φ1.5m (13# to 24# piers have
Φ1.8m), cast-in-place pile foundation, partial tie beam or bearing platform,
circular pier stud (Φ1.5m and Φ1.2m), bent cap. The embedded ribbed slab
abutment is adopted for 0# abutment. The upper structure form is: precast and
installed post-tensioned prestressing simply supported-to-continuous small box
girder, cast-in-place prestressed concrete box girder and cast-in-place common
concrete box girder. The bridge deck pavement is 6cm C40 waterproof concrete.